Oshen vote continues on school project cost figures
The board tabulated a total cost of 2,764,800 with detailed line items including construction 2,348,580 contingency 30,720 and parking lighting 9,500. Bid contracts must be signed February 11, voting runs February 2 to 9 in the high school lobby, with registration January 19. Public meeting January 17. President Harold Jonas urged prompt approval, stressing educational value and long term utility for children.