Defense Waste Processing Facility project update
The SRP report notes design at 54 percent and construction under 2 percent with $870 million cost. Completion 1988 and operation in 1989, to solidify radioactive waste into borosilicate glass for disposal. 2,600 jobs. reinforcing bars for a 10 foot thick pad being installed. L-Reactor 1 000 Acre Cooling Pond has all permits and site prep under way for a once through cooling pond.