Joint project on Michigan Avenue los early 2024 schedule
Consumers Energy city and MDOT outline a multi phase plan for downtown Marshall along the I-94 Business Loop from Sycamore Street to Marshall Avenue. Gas main upgrades start in March lasting into June followed by water main and sidewalk work through September with MDOT repaving from September into October.