Enrolment Surges At Windrem School Reaches 526
Enrolment at Windrem School stood at 526 at noon with 12 to 14 more to register. Projections suggest 600 once term begins as a four room annex remains unfinished. Principal John Bastin and Vice Principal Adye oversee classes with 150 students using the auditorium and outdoor facilities.
MENTIONED IN THIS ARTICLE
Windrem
John Bastin
Adye
Chetwynd
Paving Contract Awarded for Hudson Hope Road
Peter Kiewit accepted a $400 000 contract for paving the road from Hudson Hope to the Portage Mountain dam site. M Leansan Carnell announced the award and named Kiewit as major contractor for the project. Senior baseball finals in the BY League at Chetwynd ended in a split with Groundbirch 12 11 and Cubs 17 14 necessitating a final game.
MENTIONED IN THIS ARTICLE
Portage Mountain Dam
Hudson Hope
Chetwynd
Groundbirch
Cubs
Hydro Plant Work Begins in Chetwynd
BC Hydro and Power Authority has started excavating for a new plant in Chetwynd to house two 3000 kW units with offices. Completion is aimed for late March 1964. The text also notes a ground birch game with two Sunday matches, Gordy Doucette hitting two home runs in the second game.
MENTIONED IN THIS ARTICLE
Chetwynd
Gordy Doucette
Bridge project contract set for Peace River span
MeL A Stan Carnell, returning from Victoria, announced a contract of about 1.626 million dollars for a bridge over the Peace River near Hudson Hope to Mordhorst Sonstruckken. A start is planned within days with completion in fifteen months, with sub contracts for approaches and road work and tenders to follow once soil surveys are completed.
MENTIONED IN THIS ARTICLE
Mel.a. Stan Carnell
Victoria
Peace River
Hudson
Mordhorst Sonstruckken
Reg. Pearen
Pearen
Mordhorst Construction
Chetwynd
the Hope
Carnell
Also Mentioned on This Page
Kiewit
M.lean Stan
Peter Kiewit
B.C. Hydro and Power Authority