Monroe Waste Treatment Plant Update
The Monroe Waste Treatment Plant renovation began in April 1973 and was largely finished by December 1974. Total cost reaches 1.24 million with 55 percent federal, 25 percent state, and 20 percent city funding. capacity more than doubles to 3.5 million gallons daily, dipping to 1.7 million in off-peak. The plant, monitored weekly at six stations, faces issues from high strength industrial waste, with help from a DNA program and a consulting engineer.