Tazewell Four Lane Route 460 Beginnings and Delays
The 1966 Route 460 project in Tazewell County began 0.695 miles west of the Buchanan line and extended 5.383 miles. Adams Construction and W and H Contracting led the first phase costing 2,816,685.11 dollars from January 10, 1966 to June 5, 1968.
MENTIONED IN THIS ARTICLE
Charles Hankins
Tazewell County
Buchanan-Tazewell County
Buchanan
Tazewell
Adams Construction Company
W. and H. Contracting Company, Inc
Buchanan-Tazewell
Richlands
McDowell, Purcell, Inc
Oman Construction Company, Inc
Cedar Bluff
Road projects reshape Route 460 and Tazewell bypass plans
The report details multiple highway contracts in Virginia and Kentucky including Route 460 segments near Richlands and Claypool Hill, costs from $1.7 million to $371,658, and a 0.379 mile section near Pisgah. It notes delays, schedule shifts to 1972 1973, work by Appalachian Construction Company and Albert Brothers, and relocation of homes around Carline and Fairground.
MENTIONED IN THIS ARTICLE
Bluff
Cedar Bluff
Richlands
Claypool Hill
Highway Department
W and H Contracting Co., Inc
McDowell-Purcell, Inc
Front Street
Kents Ridge Road
Clinch River Bridge
Appalachian Construction Company
Molly Harper
Pisgah
Midtown
Cliffield
Tazewell
Jeff Higginbotham
State Highway Department
Higginbotham
Albert Brothers Contractors
Carline
Cavitt’s Creek
Cavitts Crek Dam
Bluefield
Oman Construction Company, Inc
Sam Finley, Inc
Lawford Brothers, Co., Inc
Bluestone River
Allegheny Construction Company
Also Mentioned on This Page
Red
Cedar Bluff and
Will
Pounding Mill