Aurelia to Build Fire Station Under Public Bidding Project
Aurelia Iowa council approves plans by Carlson and Hyndman for a rectangular concrete block fire station. Bids due August 13 1962 with 5 percent bid bond and 90 percent progress payments. Final 10 percent due after delivery and acceptance. Iowa content preference applies. bond 100 percent. project to start by September 1 1962 and finish by December 1 1962.