Schwalle decision deemed prudent by WSRC president
Ambrose Schwallie, president of WSRC, says delaying the $5.6 billion NPR decision is prudent amid changing world events and Bush’s nuclear cuts. He notes readiness to restart the K Reactor within two weeks and the company’s aim to accept missions from other plants to reduce government costs and mortgage. Environmental and economic pressures favor consolidating materials production and cleanup options.
MENTIONED IN THIS ARTICLE
Department of Nee
U.S
Bush
Energy
James D. Watkins
Ambrose Schwallie
WSRC
Schwallie
SRS
Schwalbe
DOE
Adm
Watkins
Westinghouse Savannah River Company
Heavy Water Reactor Plan Tied to SRS Technology Ties
Ebasco Services leads a consortium including Westinghouse Bechtel and Babcock Wilcox to design a heavy water reactor at Savannah River Site to produce tritium. The $135 million contract with Westinghouse covers project engineering with 800 to 1000 jobs and a possible total value of 300 million.
MENTIONED IN THIS ARTICLE
Savannah River
SRS
Ebasco Services Incorporated
Ensearch Corporation
Companies
Ebasco, Westinghouse, Bechtel, Babcock & Wilcox, Combustion Engineering
Rockwell
Battelle
Ebasco
Aiken
Silver Bluff Road
Augusta
Westinghouse
Savannah River Company
Aone
Gas Cooled Modular Reactor Aimed at Tritium Production
The plan centers on a modular high temperature gas cooled reactor using a graphite core cooled by helium to produce tritium. CEGA consortium led by General Atomics includes ABB Combustion Engineering Stone and Webster and Burns and Roe. The design mirrors Peach Bottom 1 and Fort St. Vrain concepts with four to eight underground modules sharing facilities and featuring active and passive safety systems.
MENTIONED IN THIS ARTICLE
If Designers
CEGA
General Atomics
Abb-Combustion Engineering
Stone and Webster Engineering Corporation
Burns & Roe Company
DOE
United States
Pennsylvania
Fort St. Vrain
Colorado
Local leaders react to NPR delay impact on Aiken area
Community figures including Mickey Smith Dr Paul Blowers and June Murff express concern over a two to three year postponement of the NPR site decision. They warn of economic effects at SRS and job losses if projects stall and urge preparation and continued diversification.
MENTIONED IN THIS ARTICLE
Iam
Defense Department
Paul L. Blowers
Aiken Technical College
NPR delay unsettles Aiken County business leaders
Aiken County Council Chairman Carrol H. Warner and Economic Development Partnership chair Tommy B. Wessinger voiced disappointment at the DOE pause on an immediate NPR start. They said the Savannah River Site remains central to defense programs, but the two-year delay leaves NPR and other sites in limbo, hurting local investment and planning.
MENTIONED IN THIS ARTICLE
Aiken County
Carrol H. Warner
NPR
Savannah River
Department of Energy
SRS
Warner
Tommy B. Wessinger
Economic Development Partnership
Aiken
Edgefield Counties
Wessinger
Soviet Union
U.S
Also Mentioned on This Page
Schwalle
Roddie Burris
Elizabeth L. Boineau
Mickey Smith
Aiken Regional Medical Centers
Thomas L. Moore
Ron Bolton
Butler Derrick
June Murff
Greater Aiken
New Ellenton
Moore
Bolton
Shaw
Carl Langley