Edges of Multiplex project face air quality delays
Colin Olfert-Graham discusses delays due to workplace safety and environmental testing for drywall removal. An environmental consultant suggests fresh air introduction, with mold concerns and a plan to remove concrete and rebuild the weeping tile system. A Dec 19 hockey date is optimistic. full completion likely by late January after curing and sequencing.