Project Completion Timeline and Finances for Russell Arena Upgrade
Graham Construction reports completion milestones for the Russell arena project with August 10 2012 target. Key tasks include concrete work on West floor slabs February 23 and May 12 bleachers May 12 to June 15 walking track May 22. Final costs show original 8.1 million plus 1.1 million footing investigation and 2 million BC funding plus provincial funds 2 million and 550 thousand top up, total funds raised about 9.8 million.