Bridge upgrades near completion at two sites
The project aims to finish by late August with a $750,000 budget. Construction began mid July building two one lane temporary bridges, one at each site, to replace traffic routes. Work runs mostly under bridge decks with parallel tasks as concrete sets, while drivers are asked to slow and heed flaggers around the clock.
MENTIONED IN THIS ARTICLE
Chapman
Pine Pass road upgrades on schedule near Chetwynd
Project manager George Lomas reports Pine Pass improvements are 40 percent complete with 11.2 kilometres of widening, two new bridges, and culvert replacements. The $31.5 million project aims to raise highway speed to 90 kmh and save about a half hour to Prince George, with final completion expected by September 30, 2011.