Sinkhole repairs progress at W A C Bennett Dam
Hydro engineer says sinkhole remediation near Hudsons Hope is advancing with grout-injection around two holes. At least four holes per sinkhole planned, with seismic checks and mid May completion anticipated along with tests of seepage drains pumping 15000 gallons per minute to verify function.